Project Proponent
CarbonCo, LLC
Contact: Brian McFarland, Director
Phone: +1 240 247 0630
Email: BMcFarland@CarbonCoLLC.com
Auditor Contact Details
Rainforest Alliance and IMAFLORA
Expected Dates of the Auditor’s Site Visit (Second Verification)
24 – 31 January 2017
Dates of the Auditor’s Site Visit (First Verification)
10 – 22 November 2015
Dates of the Auditor’s Site Visit (Validation)
9 – 20 December 2014
Public Comment Period (Validation)
31 October – 30 November 2014
Public Comment Period (First Verification)
7 October – 6 November 2015
Public Comment Period (Second Verification)
14 December – 13 January 2017
No comments received
- Acre, Brazil
-
Verification Approved - CCB Standards Third Edition, Climate Adaptation, Community and Biodiversity Gold Levels (16 February 2016)
Implementation Period: 2 August 2012 to 31 December 2014
Validation Approved – CCB Standards Third Edition, Climate Adaptation, Community and Biodiversity Gold Levels (15 April 2015)
Under Verification - Environmental Services, Inc.
-
English
English Summary
Portuguese
Portuguese Summary
VCS Monitoring Report (01 January - 31 December 2015)
Verification Statement - 15 February 2016
Verification Report - 15 February 2016
Project Implementation Report - 28 January 2016 (English, Portuguese)
VCS Verification Report - 15 February 2016
Project Implementation Report - 10 September 2015
(Portuguese summary, English summary)
Project Implementation Report - 27 August 2015(Portuguese )
Project Implementation Report - 7 August 2015(English)
Validation Statement - 15 Apr 2015
Validation Report - 15 Apr 2015
VCS Validation Report - 06 Apr 2015
Project Design Document (Portuguese Summary) - 14 Oct 2014
Project Design Document (English Summary) - 14 Oct 2014
Project Design Document (Portuguese) - 08 Apr 2015
Archived Project Design Document (Portuguese) - 14 Oct 2014
Project Design Document - 05 Mar 2015
Achieved Project Design Document - 14 Oct 2014
Project Implementation Report - 01 January - 31 December 2015